May 14, 2004 07:07
Its the strangest thing. While working ISF I see great similarties between some people here and other people I have worked with at other places. Basicly there attitude and how they work. Its kinda scary but ain't terrible.
ISF has been fun so far. Ewing hasnt been that bad except for the water. The drainage is all F!$#@ up out there. Chad has been doing Gant (sp?) (it breaks down what everyone is doing by hour.). Well anyway after the second day I think we where a .5 day behind. Well after that dat they redid the schedual since they realized they set impossible goals. Then yesterday at the end he said we where 15 min ahead. I think this really isnt because we worked harded but the schedual changed. but we did get alot done. Its always a good idea to take the extra 15 min of planning inorder not have about 1 hour of work later fixing it.