(no subject)

Sep 06, 2009 19:52

Некоторые добавочные сведения о профессиональном стиле архитекторов RMJM:
В Европе они прославились скандалом при строительстве здания шотландского парламента (Holyrood scandal) - тоже, кстати, в городе (Эдинбурге), центр которого является объектом Всемирного Наследия. Специализация у них такая?

Впрочем, там основная суть проблемы была не в нарушении городских панорам, а в том, что здание было закончено на три года позже и с превышением исходной сметы, указанной архитекторами, в ДЕСЯТЬ раз. Это меня впечатлило.

Подробная табличка, которая показывает, как это происходило (отсюда)

Date Cost Reason 24 July 1997 c£10m-£40m[24] The first cost projection provided by the Scottish Office is for housing MSPs in a new Scottish Parliament. The estimate takes no account of the location or design of any new building.[68] 6 July 1998 £50-£55m[69] The design of Miralles is chosen and the revised estimate updates the preliminary figure recognising that the initial projection was based on a cleared site of 16,000 m² (172,222 sq ft) on brownfield land in Leith, Haymarket or Holyrood.[70] The figure does not include VAT or site acquisition costs.[69] 17 June 1999 £109m[24] First Minister, Donald Dewar provisionally estimates the costs at £109m.[69] The increased figure takes account of consultancy fees, site costs, demolition, VAT, archaeology work, risk and contingencies.[68] 5 April 2000 £195m[24] Cost projections increase by £86m.[69] November 2001 £241m[24] The new figure is officially announced and takes into account increases in space and major design changes resulting from a changed brief over the previous year.[71] Rising costs are also blamed on construction problems ahead of an attempt to try to complete the building project by May 2003.[68] The then Presiding Officer Sir David Steel informs the Finance Committee of the Scottish Parliament that rescheduling work is increasing costs.[71] December 2002 c£300m[24] A cost increase to £295m in October 2002, is reported to be due to increased security needs, requiring that bombproof cladding be incorporated into designs for the external fabric of the building.[21] Rising costs are also put down to "hidden extras" in the construction process and by December 2002 "ongoing delays" raise costs above the £300m barrier.[21] The completion date for the building slips again, and plans for a grand "Opening Ceremony" are shelved indefinitely.[21] September 2003 £400m[24] In July, the new Presiding Officer, George Reid produces the first of his "monthly reports" on the cost and schedule of the building, and provides a figure of £373.9m.[69] The new figure comes in the light of reports that consultancy fees for the project top £50m.[68] By September costs break the £400m barrier and are blamed on construction problems in the interior of the building.[68] February 2004 £430m +[24] Costs are revealed to have increased again due to further problems with construction.[21] The official opening of the building is tentatively put back again to some time in 2005, however the building finally opens in October.[68] February 2007 £414.4m[9] The final cost is announced by the Scottish Parliament Corporate Body, a reduction of £16.1m on the previous estimate.[9]
Википедия больше ни о чём таком скандальном не сообщает, кроме претензий к эклектичному стилю, который призван был отражать национальный шотландский характер, а отражает... ну, я не специалист, посмотрите сами. Но знакомые подсказывают, что претензии есть и к "энергоэффективности" здания, точнее - к полному её отсутствию, и даже пишут о таком казусе, как треснувшая над залом заседаний потолочная балка - прямо в ходе парламентских дебатов :)

Если считать, что газпромовские деньги к нашему карману никакого отношения не имеют, то и ладно - одна банда ограбит другую, и шайтан с ними. Но Газпром так претендует на особое место в нашей жизни... и чтобы мы его любили... Просто сердце болит от тех убытков, которые они понесут.

охта-центр, газоскреб

Previous post Next post
Up