First half of December's addition and remodeling progress...

Dec 17, 2016 20:53

We're finally able to see a little bit of light at the end of the tunnel, and we're pretty sure it's not a train coming back at us. We're in the stage now where everything is very exciting.

Our last update for the October and November progress was quite recent, so you probably don't need a refresher.

And, if you're interested, you can see all of my blog entries about the project, which started back in June.

The executive summary of the progress for these first 2 weeks of December is:
  • Shower walls and tile
  • Appliances "ready to go"
  • Deck poles and flooring
  • Cabinets
  • Mud sink
  • Countertops
  • Wet bar
  • Porch and deck railings

December 1, 2016 - Master shower walled in


December 1, 2016 - New kitchen sink, microwave, range, and dishwasher
waiting in the garage (amidst a good portion of the rest of our house
that's been "stored away" during this renovation and addition)


December 5, 2016 - New deck poled and flooring started


December 6, 2016 - Tiled-in master shower


December 9, 2016 - The first of the cabinets installation


December 15, 2016 - Deck and porch railings being installed


December 15, 2016 - Mud sink installed in laundry room


December 16, 2016 - Countertops on the "fridge side" of our new galley kitchen


December 16, 2016 - Countertops on the "range/microwave/sink/dishwasher side"
of our new galley kitchen


December 16, 2016 - Eight 4-ft. tall by 2-ft. wide by 1-ft. deep pantry cabinets
with adjustable shelves


December 16, 2016 - And we have a wet bar! (Well, it'll be wet after
the sink and faucet are installed. Bar fridge coming, too.)


December 16, 2016 - The rest of the railings on the (soon-to-be) screened-in porch


Coming soon: Back splashes, floors, appliances, and interior walls painting...