September's addition and remodeling progress...

Oct 04, 2016 11:52

It's been a very productive month, about which we couldn't be more pleased and excited. If you need a refresher of where we last left our heroes, you can skim through the pictures in the September 5 update.

People kept asking us how many square feet we were adding on, and we finally got tired of answering, "We don't know," so we contacted the architects who informed us that we're going from 1000 square feet to 1,500 square feet. Hooray!

The executive summary of this month's progress is:
  • Framing of new areas (porch, master bathroom, master bedroom closet, storage areas) completed
  • Water heater moved
  • Existing kitchen demolished
  • New plumbing roughed in
  • New electrical wiring roughed in
September 2, 2016 - Screened-in porch framing


September 4, 2016 - Kitchen, master bathroom, and master bedroom framing


September 6, 2016 - Porch roof framing


September 8, 2016 - Porch roof


September 15, 2016 - Skylights / solar tubes arrive


September 16, 2016 - Kitchen and master bathroom skylights


September 16, 2016 - New roof over back storage shed, porch, and master bedroom
(as seen from our neighbor's yard)


September 17, 2016 - Fridge and microwave moved into the living room
in advance of the kitchen demolition


September 17, 2016 - Bob removed cabinets, counters, and the stove!


September 17, 2016 - Bob also removed the island that was in the kitchen!


September 19, 2016 - Kitchen back wall, sink, window, and cabinets demolished


September 19, 2016 - View from old kitchen opening into
new galley kitchen area replacing it


September 19, 2016 - Diana and Rollo at work


September 26, 2016 - View from existing TV room into new master suite
(hallway in middle, closet to the right, master bathroom to the left, bedroom in the back)


September 26, 2016 - New storage area in the hallway
that leads to existing bathroom


September 29, 2016 - Back of house (master bedroom, porch, and shed) walled and roofed


September 30, 2016 - Exhaust fan and canned lighting in new master bathroom


September 30, 2016 - Electrical work roughed in


September 30, 2016 - Plumbing work roughed in


September 30, 2016 - New air intake facing the master suite hallway


Coming soon: Insulation, sheetrock, floors, and cabinets...

remodeling and addition